Ekiti residents to enjoy light as State no longer depends on national grid

The Ekiti State Independent Power Project (IPP) has commenced operations with a successful test run.

A statement by the government said the IPP project has been tested successfully for two weeks, distributing 700 kW out of the total 3.5 megawatt capacity, leaving room for expansion.

According to the statement, the IPP project was initiated by the previous administration led by Dr. Kayode Fayemi and completed by Governor Biodun Oyebanji.

“This initiative aims to address the shortage of electricity supply in the state and reduce sole dependence on the national grid for electricity generation.

“The power generation concept, under the Public-Private Partnership (PPP), involves an electricity generation firm, Fen-Church Power Nigeria Ltd, building the power plants and generating electricity sold to the state for consumption. Private entities can also participate on a willing buyer, willing seller basis.

“The independent power arrangement will guarantee power supply to essential public facilities, including the Ekiti State Teaching Hospital (EKSUTH), Ekiti State University (EKSU), identified primary and secondary healthcare centers, streetlights along major roads, and booster stations, among others.

“The IPP project offers 24-hour uninterrupted power supply, making it a reliable source of electricity for individuals and corporate organizations. The project includes underground distribution networks, substations, Ring Main Units (RMUs), and multiple generating sets, with room for further expansion.

“The project aims to promote industrialization, socio-economic development, and good governance in the state while reducing costs and environmental pollution by replacing generators for public facilities.

“The government has also restored electricity to areas such as Ekiti East and Gbonyin (Ayekire) LGAs after 15 years of blackout. Additionally, the tourism hub in Ikogosi, Erijinyan, and Ipole-Iloro has been reconnected to the national grid after nearly two decades of power outage.

“The government prioritises stable electricity supply across the state to support the growth of Small and Medium Scale Enterprises (SMEs) and boost the local economy.

“The Government of Ekiti State continues to lead as a model sub-national government with a commitment to creating an attractive destination for work, living, and investment,” the statement said.